on 2008 Feb 15 8:40 AM
Hi MM Gurus
we are purchasing the cables. the prices of cable changes as per the market price change in copper in every month. how PO prices can be change according the change in copper rate every month....
JK Patel
>hi buddy
>just change po value manually while creating po
>regards
>kunal
Yes, it can be done this way. However, if you want to maintain info records, you can set the "Pr. date Cat." (price determination date control) in info record to:
1. Purchase order date - PO date will determine which price to copy from info records.
2. Delivery date - For example, you create a PO in June, but your order will be delivered in July. So, in your PO, your delivery date is set to July. Your PO then will copy July pricing entered in your info records.
3. Current date
4. Manual
5. GR Date.
Take your pick.
Hope this helps.
Regards,
Anisah
Edited by: Anisah Kassim on Jun 16, 2008 9:47 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi buddy
just change po value manually while creating po
regards
kunal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
i think we need to update the price in the material master according to the market price with MR21 transaction.abd upated info record.while creating PO the price will be automatically praposed by the system.if there is more scenarios please let me know,
Thank You
Varun.T
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
we are purchasing the cables. the prices of cable changes as per the market price change in copper in every month. how PO prices can be change according the change in copper rate every month....
If your Price is going to Change Once in a Month, then you need to maintain the MMD price as Standard.
and for every period you can change the Price through MR21 Trxn..
also maintain the Info record, during PO creation the system will propose the last Price but you can change the Price as per the Current market Price...
By maintaining the Standard price, you will be able to know the Price difference for different periods..
Thx
Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Typically for non ferrous metals the process is a little more complex and requires price fixings (with due dates). In case you are dealing with alloys of any kind, it becomes even more complex as the structure of the master will be insufficient in the standard. We have built a solution for that purpose also dealing with metal book based risk management and other thing. Send me an email in case you need additional information.
Regards,
Andreas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
maintian the price in info record and u can update the price in info record using quotations recived (use the info update indicator and the quotation shold be marked for the time dependent conditions in img )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
IN THE CUSTOMISING , MAINTAIN THE INDICATOR FOR "PRICE IS CHANGEABLE IN PO"
(PB00).
NOW , DURING PO CREATION, EVEN IF SYSTE PORPOSES PRICE FROM INFORECORD,YOU CAN MANUALLY OVERRIDE THE INFO RECORD PROPOSED PRICE AND SPECIFY THE LATEST PRICE ON THE PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
have u created a blanket po and ur reciving the materail with refernce to that and for that u want to change the price?????
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.