How to Reconcile the material document with Challans
what is the process if the challan is not completed within 180 days.
case -01 FG material document is posted after 180 days completion after making the challan.
case-02 FG material document is posted within 180 days but challan is not reconciled (or) not Completed, Can it be reconciled after 180 days completion.
With Rgds,
Krishna
Request clarification before answering.
1. If you are receiving material after 180 days, then in J1IF13, system will show 'Reverse' option as you need to reverse the CENVAT which you have availed for that RM. Excise G/L settings must be there with subtransaction type '01'.
2.If you have done GR within 180 days then you can reconcile Challan after that also.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Piyush,
whether the challan is tobe reconciled even after Reversing or what?
I have one more query ,
One of my user in MIGO for a particular material document have un-checked the components @ the time of receipt of a particular FG item. where as for the remaining FG parts - components exist within a material document.
but my problem is system is not allowing me to reconcile the remaining component , it is throwing warning message for the FG material for which components are not consumed.
With Rgds,
Krishna.
Hi all,
Any inputs regarding this......
With Rgds,
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
39 | |
8 | |
5 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.