capacity requirements not shown at cm27

Former Member
0 Kudos

hi sap gurus

                     I had created resource and marked as a finite and control key allows capacities. But after process order released , when i check at cm22,cm27  capacity requirements are not shown along process orders w.r.t resource.And also even when I do mrp with lead time scheduling ,

planned orders not showing capacity requirements.Shall u give me the solution for this?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi caetano

thanks for reply

                srinivas

Caetano
Advisor
Advisor
0 Kudos

Hello

If the issue has been solved, please close this thread by clicking the green button near on the correct answer.

BR

Caetano

Answers (1)

Answers (1)

former_member218144
Participant
0 Kudos

Hi,

Check in OPU5 for plant,material type combination, whether you had marked the generate capacity requirements icon.Check also the days in the scheduling period.

The system will schedule only within this time period.

Regards

Richie

Caetano
Advisor
Advisor
0 Kudos

Hello

Check the formula defined for capacity requirements on the work center and the standard values on the routing. Also check the if control key is set to generate capacity requirements.

BR

Caetano

Former Member
0 Kudos

  thanks for the replies.my problem is solved as I mentioned formula only in scheduling tab but not  in capacity tab.

Caetano
Advisor
Advisor
0 Kudos

Hello

Thanks for the feedback! Since the problem is solved, please close this thread.

BR

Caetano