Capacity Requirements not generated in REM

former_member698542
Active Contributor
0 Kudos
159

Hi,

I am using REM. I have created scheduling paramaetrs for planned order. I have selected the Generate capacity requirements in the scheduling parameters for Rate based scheduling.

In the work center, I have selected the Relevent for finite scheduling.

When I check the Capacity evaluation, there are no capacity requirements generated even though there are planned orders created by MRP.

Thanks and regards

Murugesan

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Have you taken the MRP run with Lead time scheduling?

Also in OPU5 transaction (scheduling paramters) for the plant & order type "Generate capacity reqmnts" for details scheduling need to active. Also check the control key in OP00 mark for capacity generation. And check your capacity formula.

Then for capacity evolation use CM01.

Regards,

R.Brahmankar