Hi all,

If the WBS element is in REL status then only we can create PR & PO (Comittment Items). My question is if the WBS Element is in CRTD status can we create PR & PO , is there any configuration behind this.

Please do the needful.

Regards,

Gagan

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

standard SAP allows creation of PR and PO

if in your system PR and PO are created only on REL then the configuration setting has been done in user status control

check your status profile of the WBS in transaction OK02

Former Member
0 Kudos

This message was moderated.

virendra_pal
Active Contributor
0 Kudos

please read sap help

check out the forum posts

get your PS consultant to do it for you