Can a same item have both scheduling line and PR.

Former Member
0 Kudos

Dear Frndz,

Kindly tell me if an item can have both scheduling line and purchase reqn generated simultaneously.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If you assigned scheduling agreement to a vendor, when MRP run system will generate schedule lines.

Simultaneously through Quota arrangement, you can create P.R for that same material against some other vendor which is not having scheduling agreement.

Regards,

Dharma