Hi all,
could you please explain to me logic of dates in maintenance?
we have an issue that call dates are moving even if we dont make any changes, f. e. maintenance plans should be called on friday and starts on monday next week, but for some reason call date is moved to monday and then the whole plan is changed and moved to next day.
Thank you in advance
Plan date and call dates are calculated automatically based on cycle and start date provided for maintenance plan. Kindly restart or start in cycle the plan with new start date for getting new plan and call dates.
e.g. for single cycle: Provide start date for plan as of last maintenance completion date.
e.g. for strategy based plan: Provide the start date of plan as of last maintenance completion date and select the respective due package from start in cycle.
Scheduling Parameters in Maintenance Plan LINK: https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members/scheduling-parameters-in-...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.