calculation Duration of machine shutdown in sap PM

former_member752729
Discoverer
0 Kudos

why do not neglect the weekend in the calculation Duration of machine shutdown in SAP PM ?

HOW TO do not calculate the length of the weekend?

Accepted Solutions (1)

Accepted Solutions (1)

Oscar_DC
Active Contributor
0 Kudos

It's a bit hard to tell from the information that you're providing.

I'm assuming you've got a PM order with operations which are assigned to a work center. There's a couple of things that you've got to know before troubleshooting this:

  1. Which is the calendar selection in the order is it 0- From work center, 1- From order hierarchy, 2- From network activity?
  2. What's the factory calendar on your work center?
  3. Does the factory calendar take weekends into consideration or is it a 364, 24/7 calendar?
former_member752729
Discoverer
0 Kudos

thank you Oscar

calendar used the weekend is not take in consideration