Hello Experts,
Whenever I am assigning budget against child WBS/'s and Totaling Up, The Budget is not accumulating to the Parent WBS . Also, here was a problem of -ve Available budget against those WBS. Now, even after making the budget (Available) to +ve value, the system is not behaving accordingly.
Please suggest..
Regards,
Ankur
Request clarification before answering.
Hi,
As per the standard sap budget is distributed from top to bottom ,you are assign the budget in the cj30 at the lower level but that time system is check the all assigned and planned values assign the WBS, Open the cj30 and assign the budget and select all now check, the check indicator if the budget is grater then the distributed budget system allowed to do the transaction
Thanks & Regards
R.B.Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks To you all. It's working now.
Regards,
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Try to run CJBN - Reconstruct Availability for Projects.
Thanks
Vamshi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try running the CJEN and reconstruct the project data base and then check the budget total up in CJ30.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
39 | |
8 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.