Budget information is not available

Former Member
0 Kudos

Hi Gurus

We have a problem with the Investment Orders . When we try to do Goods confirmation in the SRM system it shows a message that No Budget information exists .

For the specific investment orders initially budget was not allocated at the starting of the year but in the month of december for those investment orders Budget was distributed

through investment mangement program .

Could you please confirm to me do we need toexecute T code Ko31 for reconstruct availability control for internal orders .

Any help highly appreciated and points are assigned .

Cheers

Ravindra .

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

HI Srinivas

Thanks for the information .

Just to inform you that we have not made any changes to Budget profile. They have changed the values in the investment

management program ,Changed the values in over all values as well as in the year wise values .

Could you please tell me in this scenario whether do we need to execute T code Ko31 for reconstruct availability control for internal orders .

Cheers

Ravindra .

Former Member
0 Kudos

You reconstruct the availability control in below cases:

1. you haved changed the availability control settings in the budget profile (e.g. from overall to annual values)

2. you have done changes to the tolerance limits for availability control.

Doing so assigned values are recalculated and references are created to orders that have budget.

If you want to activate/deactivate the availability control you need to use KO30/KO32.

Regards

Sreenivas