on 2014 May 08 9:29 AM
HI
getting Below Error
Item WBS Element XXXXXX Budget exceeded
Message BP604
When User wants to release the Budget in CJ32 he get the above error
they do Bottom up budget, Period Wise they have assigned the Budget
At first level after total up budget is 90laks, they have released only 16lak, this month they are trying to do release balance amount of 74lak
thy could not able to do, system say budget exceeded
in cj32 when its checked assigned value was 2 cr's which is more the release budget
WBS 4 level XXXXXXX Budget 1687000 Assigned 1005276
WBS 4 level XXXXXXX Budget 1900000 Assigned 18466080
WBS 4 level XXXXXXX Budget 4600000 Assigned 264621
WBS 4 level XXXXXXX Budget NA Assigned 1725420
First thing how system allowed to do commitment/actual booking more then the released Budget when Availability control was active
Kindly advice what are all the changes need to be done
Thanks
hi,
Please check SAP note http://service.sap.com/sap/support/notes/1606591.
Hope it helps!
Thank you and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.