Budget Exceed error

reena_ghadge
Participant
0 Kudos

Hi,

The Budget report shows available as 134 INR .

when i try to delete a material component the system prompts a log of  budget exceed of 2 lakhs. " IW172 budget payment exceed for wbs and network"

the reservations are already made and the value is captured against ROP now when i delete the component the reservation should get deleted and value should be reflected in budget then why this budget error

Regards,

Reena

Accepted Solutions (0)

Answers (2)

Answers (2)

reena_ghadge
Participant
0 Kudos

Hi,

Any suggestions .

Regards,

Reena

Former Member
0 Kudos

Hello Reena,

You can manually implement the coding in your ECC6 system, then execute the program t Z_DELETE_WBS_ASSIGNMENT. This should resolve the error IW172.

Regards, Gordon

Former Member
0 Kudos

Check for inconsistencies in Availability control through CJ31 > Extras > Availibility control > Analysis

Type =SUM in the command line and press enter. Analyse the values for consistency.

rgds

Saurabh

Former Member
0 Kudos

Hi

If you are using SAP version 5.0, check note 560965

Regards

Shrikant

reena_ghadge
Participant
0 Kudos

Thanks Shrikant,

It is ECC 6.0

Regards,

Reena