Budget check for the WBS assigned to the maintence orders

SAPSupport
Employee
Employee
0 Kudos

Dear Experts,

I am testing the scenario for budget check for our customer having a requirement for maintenance project but the system is not checking the budget .

A Project WBS with budget, is assigned to a maintenance order & the commitments are posted through the maintenance order. In the project budget report the budget consumption is showing but system is not checking the budget for budget overrun. (AVAC is active for the project & Project profile – Investment project) 

 

 

Regards,

Sandeep


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.
View Entire Topic
SAPSupport
Employee
Employee
0 Kudos

It's mentioned in the help portal:

"No budget availability control is available for PM orders."

https://help.sap.com/docs/SAP_S4HANA_CLOUD/bd39d476d1e34b48afed98759286efd6/d6e3c961f1464f9eac635048...