on 2009 Jun 02 4:08 PM
Hi, say a finish product requires a semi finished product which we manufacture in-house (requires a raw material to make) and a raw material. in this case we need 3 level bom required, bottom most will be raw, 2nd from bottom will be semi finished & raw mat and top most will be finished product. if we run mrp (mts with stock 0) it suppose to create 1 pr to procure 1 raw (for bottom most mat) and 1 palnned order to make semi finished mat + 1 pr to procure 2nd level bom, 1 planned order to make assemblying final / finish product.Am i correct?
if i procure the second level semi finish mat from out side, the bom suppose to be 2 level. when we run mrp, 1 pr to procure semi + raw mat (2nd level) and 1 planned order to make finish product. Pls advise whether my above assumption is correct?
Hi ys yadav ,
Yes assumption is correct, MRP will create procurement proposals based on procurement types you had assigned in material master.
E u2013 In-house
F- externally procured.
X-in-house/ external procured
If for semi finish the type is X you can either convert it into purchase requisition or plan order, as per your wish.
Hope it will help you.
Regards
Ritesh
Edited by: R S D on Jun 3, 2009 11:46 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.