on 2009 Sep 09 1:10 PM
Hi all. have the fallowing problem: Is there any possibility of blocking TECO confirmation on a production order if this production order has other production requests linked to it ?
The user should first close the production requests and after that set TECO status on the production order.
Thank you,
Cristian.
Create a status profile using BS02. Assign this status profile to Order type. This will prevent putting TECO status for production orders having purchase requisition for external operations.