Hi all
A delivery for a material was created and PGIed in Apr 2016. The material was not costed then. Now we are in May 2016, and when creating billing document, the system gave the error "No standard cost estimate could be found".I tried to create a standard cost estimate for May (as the system allows only current and future periods), but the system would still give me an error saying that no standard cost estimate was found as of April 2016.
How do I work around this issue?
I can't cancel the PGI and do it again with May PGI date. Because of internal controls we have to show the delivery in the same month the product actually left our location. Please help me fix this issue.
Thanks
Vamsi
Request clarification before answering.
Found this useful with 3 options
Giorgio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
114 | |
10 | |
7 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.