We have activated BP Z_US_SOLUTION. Now we have a requirement to activate additional scope item in this solution.
About this scenario, SAP note 2938086 states the following:
"At a later point of time, if you need more scope items to be activated, you can change the Z_CUST solution and add the scope items you need, then activate them in Implementation Assistant.”
Question:
The scope of "Z_US_SOLUTION" can be extended and the solution re-activated under the following prerequisites:
So basically, the client/system must be in the state where the last activation ended. Otherwise the changes can lead to activation errors for the added scope or manual customer configuration might be overwritten.
If above conditions are not met in the original activation client, a scope extension in the client is not supported anymore.
What it can also be done as a workaround (with quite some effort) in this case is to create a new client in the system, where he first activates the old scope again then closes the activation transport, then does the scope extension there recording changes in a new transport and move this new transport to the business client.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.