on 2011 Feb 13 1:01 PM
Hi,
I have one problem in recording BDC for MRP.For each material MRP will create onr purchase request.But while recording BDC only for one material purchasing request is being created.
Can any one pls help in order to solve this problem
Hi,
Instead of BDC of MD01 t code, you should use program 'RMMRP000' from SE38.
You can use Submit & Return command for this report 'RMMRP000' after filling selection screen parameters.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.