Hi Gurus,

Can anybody please provide details on batch program run? How do we set these program? Is there any dcoumentation which I can use?

thnaks,

Khan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

You can execute any program through background.

Initially you need to create a variant using SE38

In se38, give the program name and execute,

In the screen, enter your required parameters and save them as variant

with a name and description.

Some parameters, you may require as dynamic, eg. range of dates,

for which, select the "Selection variable - check box" against the parameter.

and press Selection variable button on left hand top.

here select the date form, it will chagne to green.

Then, you may give the date range from the pull down menu. and Save the variant.

Then enter SM36,

Give the batch job name.

Press on steps button,

Give Program and select variant.

Give user , Spool recepient and print specifications etc., to your requirement.

and for second program, pick the earlier program line item and again pick STEPs icon.You may proceed with the same step and save.

The batch job will be scheduled now.

Then enter SM37 - here you can monitor the batch jobs.

Here, you may give program name and execute,

In next screen, select the batch job and press"start conditions"

Give, batch job run date, and time and its frequency.

In case of repeat batch job, please select periodic values and save.

and save the batch job.

Now, batch job is released and will run in the time and date specified.

Hope this helps you

Regards

Sasi

Former Member
0 Kudos

Hi Khan,

You will get the material in the first thread of this forum by mohammed arif.

rewards if helpful

regards

venkadesh