on 2008 Nov 19 6:17 AM
Dear All,
This is regarding Batch number that the system generates internaly at the time of Goods receipt,but the same is not generating the batch number.
I checked all the configs but i could not trace it out.Can any one help me to solve the issue.
Thanks in advance,
With Regards
Vinod
Hi Vinod
1.First check the batch indicator in material master purchase view
2. Active internal no batch assignment. ( LG-BATCH MANAGEMENT-BATCH NUMBER ASSIGNMENT)
Active the batch assignment
Maintain the internal no batch assignment
If you check this few things you will pick the automatic batch no.
Regards
Laxman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Follow the steps:
1.Field---VFDAT adn table-MCHA should be created as a charecter in CT04signed to a class in CL02N.
2.create MM01 and add the class to it in classification view.
3.In mm01 plt storage1 view give data for remainning shelf life and total shelf life and in purchasing view activate batch management.
4.OMJ5- activate SLED for your plant and mvt type 201.
5.opj2- set BD for your plant.
6.create sort sequence in cu70 and assign your charecteristic value to it.
7.create batch serch strategy in MBC1 for access sequence(plt/matrl/mvt typ) create a condition record.
8.Do a GR using 501 and enter SLED related details.(production date and exp date values)
Repeat the above step and enter diffrent values for SLED details.
So now two batches are created with SLED as the charecteristic.
9.Do a GI using 201 mvt tye in MB1A and enter * in batch field(system will determine the batch using the SLED value basedon the criteria(ascending or descending which was set in the sort rule.)
Reg,
Deepak.
Hi Vinod,
Go through below path and find whether you have activated Batch Creation with Movement type 101 or not.
SPRO ---> Logistic --> Batch Management ---> Creation of New Batch ---> Define Batch Creation for Goods Movement.
Also check whether Batch Management is activated or not for that Material.
Regards,
Dhaval
Hi,
.create MM01
.In mm01 plt storage1 view give data for remaining shelf life and total shelf life and in purchasing view activate batch management.
.OMJ5- activate SLED for your plant and mvt type 201.
.opj2- set BD for your plant.
Reg,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Please check whether the Batch Management has been activated for the materials in the said plant.
If the materials are Batch managed then u have to activate the Batch Management in the MMR.
There are the configurations to be done for this and also proper Material and Batch combinations have to be maintained for the respective plants. Only then when u execute a GR or any material movement against it it will automatically pick up the Batch.
Hope this helps.
Regards,
Prasanna
Please award if helpful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.