From where can i get the equipment available time?

Accepted Solutions (1)

Accepted Solutions (1)

former_member1107731
Contributor
0 Kudos

Iqbal,

Well, if by equipment available time, you mean that the equipment is not in operation and neither under maintenance. You can get it from Production Planning as there would be a work center created for the equipment, so using the capacity planning reports you can get the details about equipment available time.

You can also maintain user statuses at the equipment if in case Production Planning module has not been implemented so whenever the equipment is available you set the appropriate user status and using the report RSSCD100 and the object type EQUI and appropriate equipment, you can get the available time for the equipment along with other useful information.

Best Regards,

Usman Kahoot