AVAILABILITY CHECK

Former Member
0 Kudos

What is the Diff. between Dialy Requirement and Individual Requirements in Availability Check (Mat.Master)?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Daily reqmts : The total reqmts per day for one particular material.

Ex : Reqmt 1 for FERT A 10 PC on 31.07.2007

Reqmt 2 for the same material A 10 pc on 31.07.2007

Therefore one planned order for 20 pc will be created on 31.07.2007

Individual reqmts:

For reqmt 1 one planned order will be created

For reqmt 2 one planned order will be created.

Regards,

nandha