Availability Check in planned Order & Production Order

former_member228481
Contributor
0 Kudos

Dear All,

How can I achieve the same Availability Check (missing Parts ) output in Planned Order & Production Order.

Currently in Availability check in Planned Order is bit different in the sense, I have the Component in Stock without any reservation. But in Planned Order it shows in Missing part.

But if I convert this Planned Order to Production Order, it is not visible in Missing parts which is correct.

I want to have the same missing part report for both Planned Order & Production Order.

Thanks

Regards'

Raghu

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Availability check for planned orders is usually defined in OPPJ. Availability check for production orders can be defined in OPJK.

In OIn OPPJ you can assign a check rule for planned orders.

In OPJK you can assign a check rule for Production orders.

In OPJJ you can determine the scope of check for any availability check PP.

Hope clear to you.

regards,

R.Brahmankar

former_member228481
Contributor
0 Kudos

Dear Brahmankar,

Thanks for replay.

Now i did, the said possibility, in OPJK is different from my Regular material master rule.

When i see, availability in MD12 it shows the material available, and same as in Production Order check as well.

But when, I use MDVP, for check. the same planned order shows the same component as missing.

am i on the right track?

Please suggest.

Thanks

Regards

Raghu

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Yes please check you have maintained the following

OPPQ in dependent reqmt availability push button ,,,whether you have maintained the checking rule it should be same with OPJJ setting.

Also refer this thread,

Regards,

R.Brahmankar

former_member228481
Contributor
0 Kudos

Hi,

Yes Its there in my case for Plant I am using PP as rule with 02 combination. 02 is there in all materials.

At plant level rule is, PP.

For Production Order I changed it to 01 with respect to Order Type.

So the Missing parts for Production ORders is tuning with Planned Order(if I check in MD12)

But when i use MDVP, the same component is shown as missing.

Thats the Problem

Thanks

Regards

Raghu

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the setting of OPPJ

Regards,

R.Brahmankar

former_member228481
Contributor
0 Kudos

Dear Brhamankar,

Kindly le me know which particular i am missing here.

For stocks i have included : Safety Stock, Stk in transfer, Quality Ins Stock.

Mor Movements : All tick mArks and

Incl.depen.reservat. X Include all res

Incl. production orders X Take all production Orders

And Check without RLT is activated.

Please elaborate if i m missing anything.

Regards

Raghu