Dear All,

I am using subcontracting Scenario for semifinished product. For this i am making purchase order for this material But How to check availability of Bom component which is used in P.O. for subcontractor. Because it very hectic to check every material for bom in MMBE. If any solution pls revert back with Proper Solution. Thanks in advance.

Regards

Atul

Accepted Solutions (1)

Accepted Solutions (1)

csaba_szommer
Active Contributor
0 Kudos

Hi,

MRP controller / purchaser / etc is responsible for material availability.

You can use MD04 "individual" and / or "collective access" to check the stock / planning situation. ME2O can also be used to manage the special stock segment.

No other tool is possible as per my best knowledge.

Regards,

Csaba

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear ZOD,

You can check the availability of BOM Material through the Pur.Order.

Just do the following steps-:.

Open pur.order - Item details (at bottom) -click on material data Tab page,select Component,next screen select the row & click F2,at bottom of that screen there is one button for Availability check click on that,at next click on ATP Availability & then overview stock.

You will find out the result what you want.

Hope it will clear you.