Availability Check: ATP - Available To Promise

Former Member
0 Kudos

I would like to when we do Availability Check (ATP) for a particular material, does it take into consideration planned orders, purchase requisitions, production orders, purchase orders? Is giving a requirements date mandatory for the Availability Check?

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Your scope of check determine whether system considered planned orders, purchase requisitions, production orders, purchase orders, etc...

Go to OPJJ select your checking rule and checking group here you can select the elements which you want to consider for ATP under In/outward movement.

From sales order point of view yes requirements date is required for the Availability Check.

Regards,

R.Brahmankar