Hi experts,

In my project, i have a Invoicing Plan for a External Act,

When convert from PR to PO, i want that "Invoicing Plan" detail - that created from PS - transfer to "Invoicing Plan" at PO automatically.

Kindly help me for this case.

Thanks and best regards,

NhatLQ

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

I dont think invoice plan will be copied to PO automatically from PS.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

It is not possible to have it copied automatically. You can copy it manually by filling in the field in PO Invoicing Plan 'Reference' with invoicing plan number from PS Invoicing Plan. You can store the number in Purch.Req. tracking number. Unfortunatelly this is all manual work.