Automatic MRP to run for CBP when stock falls below reorder point

Former Member
0 Kudos

Hello Experts,

We have manual reorder point planning(VB) for one of our clients,But there is a requirement which wants MRP to run in background for the material whose stock falls below Reorder Point.Need your Inputs to achieve this??

Thanks & Regards,

Gopal Attal.

View Entire Topic
former_member184627
Active Contributor
0 Kudos

Hi Gopal,

There is no automatic MRP run which takes place when stock goes below the reorder point.

Suggest to schedule a daily background job using transaction MDBT (Program RMMRP000), which will take care of the requirements & plan accordingly whenever the stock goes below the reorder point.

Regards,

Senthilkumar SD