Automatic assignment of Main Work Center in WO's

Former Member
0 Kudos

Hi gurus,

We massively uploaded PM plans and launched the WO's.

Per default the system assigned the Work Center at Equipment level. Any idea how to change this setting?

Thanks,

VL

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi VL,

In ECC 6.0 tcode IW38. execute tcode as per your required input parameter and get out put.

For output at top go to Order>>>>Mass Change.

There you will get option to change maintenance work center for all order.