Hi Expert,

Can we do auto UD base on in process inspection lot. suppose if 03 lot accepted then 04 lot for related to same production order will be accepted as auto UD & vice versa

View Entire Topic
aniket_gautam
Participant
0 Kudos

Hi Yogananda,

Thanks for your help. I need auto UD should happen for 04 lot based on 03 UD. If 03 is accepted then 04 should automatically accepted in background. If 03 is rejected then 04 UD is rejected automatically. Because we have lots of lot generate based on pallet GR. If 10 time GR done we will get 10 lot for same production order. So pallet by pallet we have lot so as 03 already process with RR and UD we don't need to do UD for 04.