on 2012 Dec 19 12:09 PM
Hi Gurus...
Recently my client changed his holiday calender now he want to run availability check for multiple open sales orders which are due for delivery.
Is there any transaction where i can run the availability check for multiple sales ordes with single transaction. is it possible or have to do one by one.
Please advise..!!!
Thansk in advance.
-Kishore
Hi Kumar
Go to V_V2 and instead of entering the material, enter the plant you want to run the availability check for,
in the options menu select only Process sales documents
execute.....
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kumar,
V_V2 for sales orders.
As mentioned by expert Raneesh, you should also probably review your planned and Production orders as well.
Best regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try in t-code COHV OR MDVP
Raneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.