Assessment(Actual) for secondary elements(Plan)

former_member193513
Contributor
0 Kudos

Hi All

We are running actual Assessment cycle KSU5. When we try to run for only secondry cost elements, for plan data, it is not picking sender values. When I run the report S_ALR_87013611 - Cost Centers: Actual/Plan/Variance , I can see that there is plan cost in the system.

KP07 also is not showing any data for Secondry cost element.

Can some one help us with where this plan data is comming in the variance report but not getting picked in Assessment and KP07.

Thanks

Prasad

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi,

Are you allocating plan data? Then, you should use KSUB.

Regards,

Eli

former_member193513
Contributor
0 Kudos

Hi Eli

in KSU3, you may see that each segment may be run either for actual or for plan data. In our case when I run KSU5 wiht actual it is sucessful. While running in plan option, it does pick up primary cost elements, but is not secondry cost element. any specific reasons?

Regards

Prasad

iklovski
Active Contributor
0 Kudos

Please, clarify whether you want to allocate plan values (i.e. transfer planning from one cost obejct to another) or use them as reference? The option box you mention is relevant for the second option.

former_member193513
Contributor
0 Kudos

In any case, while doing a test run, it shouyld pick up the sender values. My doubt is why is it not picking those values in the actual assessment cycle run.