Assembly Processing - CN08

0 Kudos

Hi,

we are using assembly processing functionality which triggers a project on Save of Sales Order.

In CN08, Mateial which is assigned to standard Network & WBS we dont have any issues in triggering a Project on save of Sales Order. When a material is to be shared between countries, we use Network classification concept which

informs the system to select the right network alternative. Once the network is selected, On save of Sales Order

we get a Pop up to fill in the Billing WBS element(Which is mandatory).

We want to get rid of this pop up. Do we have any exits (or) BADI to address this issue??

Regards,

Karthik Bhaskaran

View Entire Topic
shareeq_hussain
Active Participant
0 Kudos

Dear Karthik,

Please check if you have maintained the WBS Element in your Standard Network also.

Regards,

Shareeq