Appropriation request approval

Former Member
0 Kudos

We are using investment Management for Capital Budgeting. Appropriation request are created and approved in IMA11. After approval of appropriation request system shall not allow any change by user but even after approving changes are permitted. How to achieve it in system. please advise.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Give only creation option for User's if at all the user need to do changes then make SOP as creation of new Appropriation Request by inputting Old App Rqst in the new App Rqst.