on 2008 Nov 22 9:39 AM
Greeting..
I have a material whihc is having 5 opeartion. Now in scheduling system first schedule first opeartion n calculate start & end date of first opeartion.
Now for second opeartion .......end date of fisrt opertion is the start date of second opeartion and by ading satndaed time finish date of second opearation..and so on..
Now how to set the common date as production order start date for all opeartion So the each opeartion will start on Produciton order start date.
Please give ur input
Hi,
Select the radio button "Continuous flow production" in Overlapping tab in the operation details of all the operations. Now all the opeartions wil start and end with the same dates.
Check the above if it suits for your requirement.
-Thaila Shree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.