Actual Cost

0 Kudos
72

Hi,

I attached one material to the WBS-activity and created scenario PR -> PO -> GR -> GI / delivery.

The value is showing in actual cost.

Please anyone can suggest me the name of table, so that i can track the actual cost using GI / delivery.

Regards,

Vikas

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello ,

Use COSP or RPSCO table.

Regards

Keshav

0 Kudos

To get actual cost using table COSP or RPSCO, we have to pass object number or cost element.

But i want to pass GI or delivery number.

Is there any table for the same ?

Regards,

Vikas

Former Member
0 Kudos

Hi, Vikas!

Have you tried to take a look at COEP table? If you cannot get the information you want directly in COEP, I'm afraid you'll have to go to BSEG table, which is not a good idea... If you have no other option and you'll use BSEG for that anyway, you should consider using an Index for better performance.

Regards,

Ivanna

Former Member
0 Kudos

Hi,

Pass the OBJNR in the RPSCO table selecting value type 4 to get the actual cost. Double click on the line item that shows the required value. Check if there is something as a reference document number. Try passing this in COSP and check. Else you can check out the BSEG table, which even i feel is not a better option.

Regards,

Gokul