on 2015 Jan 09 5:59 AM
From Which table i will get Actual and Commitment cost of a WBS.
Hi Shailendra,
For Plan Cost of individual WBS; we should pass WBS as input to PRPS-PSPNR and obtain the PRPS-OBJNR.
After fetching the PRPS-OBJNR, pass this value to RPSCO Table, RPSCO-OBJNR with value type RPSCO-WRTTP = 1 and get Plan cost for WBS by adding the value obtained in the following fields of RPSCO table WLP00, WLP01,...to.... WLP16.
Also find the below link
Planned Cost and Budget - RPSCO Table Details - Product Lifecycle Management - SCN Wiki
Regards
Rajkumar Narasimman