Actual and Commitment Cost of a WBS

former_member197132
Participant
0 Kudos
448

From Which table i will get Actual and Commitment cost of a WBS.

View Entire Topic
rajkumarnarasimman
Active Contributor
0 Kudos

Hi Shailendra,

For Plan Cost of individual WBS; we should pass WBS as input to PRPS-PSPNR and obtain the PRPS-OBJNR.


  After fetching the PRPS-OBJNR, pass this value to RPSCO Table, RPSCO-OBJNR with value type RPSCO-WRTTP = 1 and get Plan cost for WBS by adding the value obtained in the following fields of RPSCO table WLP00, WLP01,...to.... WLP16.

Also find the below link

Planned Cost and Budget - RPSCO Table Details - Product Lifecycle Management - SCN Wiki

Regards

Rajkumar Narasimman

former_member197132
Participant
0 Kudos

Hi Rajkumar,

I am not getting acutal and commitment cost.

Is there another way available ?

Regards

Shailendra Karada