on 2009 Jan 27 6:18 AM
Hi,
I need the solution like this. Our fiscal year April to March. We want the actual activity prices of the April should be planned for the May month. And may month actual prices should be planned for the next month. Like that we want use our activity prices.
For this where we have to configure and what transaction codes we have to run in month end.
please guide me
Sateesh
Sateesh,
Use KP98 to transfer actual values of one period as planned values for another period.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use t-code KP26 and plan the price for particular period.
Regards,
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.