Dear PP Gurus,

I have assigned milestone confirmation to Last operation and during Confirmation of process order, System is not proposing time for one operation activity but for others it is proposing. I am using same control key for other operation also. and for last operation Control key is milestone operation.

At process order operation details, system copies values from recipe. and gives standard values for process orders for all operations including the one where no proposal at confirmation

Can anyone guide me.

Regards,

Pradeep

Edited by: PRADEEP on May 18, 2011 1:29 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Pradeep,

Check process orders or master receipies if standard values are maintained against the operation/phase. which you are confirming.

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear PP Gurus,

Issue resolved. Base Quantity was 20000 and calculations for particular activity was more than 3 decimals. So system is not proposing any activity calculation during confirmation.

Regards,

Pradeep

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

System is not proposing time for one operation activity but for others it is proposing

Check in process order itself. Select operation/phase line item and go to operation details.

Here go to qty/activites tab. and check values for activity values are available in To Confirm or not?

Regards,

Dhaval

Anupam1143
Active Contributor
0 Kudos

Hi

Check In Confirmation parameters in OPK4 >indi entry of operation w int screen select Under activities propose and in also in OPK1 under default> default> quants and services> immediate proposal.

Regards