Dear All,

My question it's regarding at activity in work centers.

I defined "setup time" like first activity, and I established an value for the plan price, for the activity type.

Normally, this setup activity it's applicable just for first piece and for the rest no!

But now, if I intend to produse 100 objects, this setup time it's multiply by the number of pieces.

Can somebody to say me, how can I configure thus the setup time be applicable just for one piece.

Thank you, very much!

Marian

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can use the formula SAP005 = setup x operation split for Capacities & SAP001 = Setup for scheduling. In this case it will not consider the operation quantities & will calculate setup irresepective of operational quantity.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,,

Actually the formula which you are defining at the costing view is giving the error.

Create the varable with first st value and create a formuls with only the variable and assign it into the costing field of work center.Then the system will take the value of the activity time only once.

First define a parameter in transaction OP7B . Change the standard value key and give the parameter in OP19.Define a formula in transaction OP21.

Hope it will help you.

regards,

kaushik

dhaval_choksi3
Active Contributor
0 Kudos

Hi ,

In such cases you can use Parameter SAPC04 - Fixed duration for that specific Operation and work center.

Just maintain the required time to complete work for that one piece only.

Regards,

Dhaval

Former Member
0 Kudos

so set up time is constant for all operation qty,

just u create new set up time formula,copy the sap002 ,in that delete the operation qty and base qty ,

so ur formual will be only mchine time,so irespective order qty ,mahicne will be same