Activity based costing

Former Member
0 Kudos

Dear Guys,

In maintenance workcenter in the costing tab,I have maintained Cost center 500(admin cost center)with activity INST(I have definedRs 500 /hr in KP26).

Iam using this workcenter in Maintenance order for equipment XXX(cost center-200 in account assignment) and upon releasing the order , settlement rule will get created for cost center 200.

The total operation hours confirmed is 20 hours and on settlement ,Rs 10000(500x20) is settled on cost center 200(responsible costcenter for equipment).

Then what is the point of giving Admin cost center in Maintenance Workcenter?

Is it required only for assigning activity type in KP26?

I request you to clarify this please .

Regards

ISWARI

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi iswari

yes you are correct, the cost center specified on the work center (master data) is used for planning for the cost center and activity in KP26.from which the cost will be picked up,whereas the cost center specified in the order is the receiver cost center

regards

thyagarajan

Answers (1)

Answers (1)

Former Member
0 Kudos

Thank you Mr Thiyagarajan

Regards

ISWARI