Account assignment - WBS Element Responsibility

Former Member
0 Kudos
315

Hi,

I have searched MM, PS & FI forums for an answer to this but found nothing.

In Purchase Requisition, cost can be allocated to a project/WBS element (account assignment). When PR goes for approval it will always go to the person presponsible for the project and not the individual responsible for the WBS element.

Determination comes from table PROJ-VERNR.

How can I make the user responsible for the WBS element become the approver of the PR if they are responsible for the WBS element only and not the project itself.

Config done in CJ20N, OPS6.

Is there a standard way to configure this or perhaps user exit?

Thank you,

Kind Regards,

Will Conlon

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Can anyone shed any light on the actual solution for this?

Was the answer to use the user exit in PR release or was it somehow possible config?

Former Member
0 Kudos

After debugging, I found out that I needed to get my approver from PRPS-VERNR instead of PROJ-VERNR.

FYI, I will now recall my user from TJC04 table.