hi friends

i maked absence quota but this qouta deserved after 3 month from hirring date of employee how can i make this?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hai dojo,

we can perform through base entitlements by giving seniority from 0 to 3 months or also through date type specification.

regards,

chiran reddy.

Answers (1)

Answers (1)

former_member207885
Contributor
0 Kudos

Hi you ahve to write a rule for this.

Check the date type specifications infotype 0040 to get the date type for the hire date.Let's say it is 01 then,the rule should look like this

HRS=YDAA01

HRS?90

<

  • HRS=30 ADDDBZ123Z (here Z123 is time type which is linked to the absence quota in the "Set Base Entitlements " Configuration step.And I assumed that the absence quota is 30 hours.