on 2007 Mar 13 8:00 AM
Hello experts,
When I want to do the transaction MR21, I met an error message "A current or future standard price exists for material xxxxxxx". Could anyone please tell me how I can go on with the transaction MR21?
Many thanks!
Hi Christina,
It's just a warning message.
You can press enter key to skip it and change price as you want.
But remember one thing, you can not change the Standard price.
Only Moving average price can be changed in MR21.
Regards,
Worached.
Reward point is the way to say thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In MR21 you can change the price of a material with a moving average price. If the material price control is s , then the below error gets.
Thanks
Dasa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
go for T.Code:mm01 Material master you have to maintain Standered(s) or moving avarage price(v) type you will maintain.
if it is useful assigne the points as a way thanks
Regards
gvr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.