2 Step GR of Process Order

0 Kudos
334

Our plant implemented a 2 step goods receipt process a few years back, where in house production of packed goods was changed from a simple COR6 goods receipt, to a two step receipt where the production line confirmed the process order using COR6 and then the warehouse receipted this into stock using MIGO and receipting stock in against the process order number.

Where is this change applied? I have looked at material master data and the BOM, but can't find where to select this option. I know the answer is very simple, however I have completely forgotten how this was done.

moshenaveh
Community Manager
Community Manager
0 Kudos

Welcome and thanks for visiting SAP Community to get answers to your questions. While you're waiting for help, check out our tutorial to get started in SAP Community: https://developers.sap.com/tutorials/community-qa.html, as it provides tips for preparing questions that draw responses from our members. For example, you can: - outline what steps you took to find answers (and why they weren't helpful) - share screenshots of what you've seen/done - make sure you've applied the appropriate tags The more details you provide, the more likely it is that members will be able to help you. Should you wish, you can revise your question by selecting Actions, then Edit. By adding a picture to your profile you encourage readers to respond to your question. Learn more about your profile here: https://developers.sap.com/tutorials/community-profile.html

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Ryan

Usually companies activate the goods receipt during the order confirmation by setting a control key with automatic goods receipt in the last operation of the routing/recipe.

Regards,
Caetano