Please find below STD SAP Behavior for Work Order Dates Definitions.
This prepared on the basis of SDN Thread Posted on the SCN EAM Forum.
1) Basic Start - This is the date on which u want to start your work... (No calculation is involved)
2) Basic Finish Date. - This is the date on which u want to finish your work. (Priority type can influence this date. Depend on priority type. Which u have selected in order header.)
3) Schedule Start Date - this is the start date of work as per system. This date is totally depend on scheduling type..
Example - 1 in forward scheduling it remain fixed and schedule finish date & basic finish date would be varying according to the work hours in operation.
4) Schedule Finish Date - this is the finish date determined by system as per the scheduling type.
Example-1 - if scheduling type is backward, then basic fin. And schedule finish date would be same. And schedule start date would be shifted according to the work hours in operation.
In the case of current scheduling both type (basic and schedule date) of start & finish dates remains same... as per the work hour it may overload the work center capacity or it may not
If we have assigned maintenance packages to the task list and using strategy plan...
Then Order basic start date would be govern by Initial buffer in maintenance package
And basic end date would be govern by sub sequential buffer in maintenance package.
New basic start = Plan Date - initial buffer
New basic finish = plan date + subsequent buffer.
Reference Date & Time--> Date and time on which the system enters completed PM and CS orders and notifications in the history. This Date and time can be used as per User requirement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |