When we create a Production order manually or convert from the Planned order, the order type for the Production order is selected automatically in the following priority
Order type defined in the Production scheduling Profile (OPKP)
Order type defined in the Production scheduling Profile assigned to the Production scheduler (OPJ9)
Order type defined in the Plant Parameter (OPPQ)
Order Type defined in the MRP Group Parameters (OPPR)
hope, this information helps to understand the Order type selection for production orders.