Follow the below steps for doing the activation of change document.

  1. Go to spro transaction

  2. Navigate to the path Personnel Management->Organizational Management->Activate Change Documents

  3. Provide the entry as shown in the screen shot.




4. Make the changes in PP01 for the respective object and relationship.

5. Run the report RHCDOC_DISPLAY in SE38 and you will be able to see the changes made from the tcode PP01.