Hello forum,

I'm searching the code where I can change the settings of the field

'completed', so that I can change the status from 'completed' to

'open' again.

In standard it is not possible to open a completed activity.

Can anybody help me ?

Best regards

Gerd

Accepted Solutions (1)

Accepted Solutions (1)

gerd_hotz
Contributor
0 Kudos

Hi,

I use crm 50sp6. It is tileset actdeta2, field status.

Best regards,

Gerd

Former Member
0 Kudos

Hi!

I am using 4.0 - same problem

My solution was to modify to modify business rule brlsActivityModifyAllowed

....

' Activity is always modifiable

brIsActivityModifyAllowed = True

Exit Function

and the object BOActivity

the event handler loaded

ThisBO.SetAttributeProp "ActivityStatus", blAttributeNormal

the event handler saved

ThisBO.SetAttributeProp "ActivityStatus", blAttributeNormal

Please adjust to 5.0

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Gerd,

which MSA release do you use? And do you mean the field 'status' at tile 'actdeta2'?

Kind regards,

Diana