Hi gurus;
I've a problem when I execute the transaction CRM_OM_BP_INTEGRATE, because I select the ORGANIZATIONAL UNITS and when I want Start the Synchronisation Procedure, SAP give me a message, "HR integrationis not active"
That's neccesary to continue with the replication between CRM and R/3?
How I solve that?
Thanks.
Regards Miguel.
Hi,
You should activate the integration between business partners and organizational units. Goto IMG>CRM>Master Data> Business Partner> Integration Business Partner-Organization Management--> Set Up Integration with Organizational Management and Switch HRALX/OBPON to 'ON'.
Hope this help.
Thanks,
Karuna.