A | Pick Pack Time |
B | Loading Time |
C | Replenishment Lead Time [RLT] |
D | Transportation Lead Time [TLT] |
E | Transit Time |
Shipping Point |
Plant |
Sales Org |
Customer |
TABLE about the Checks for each Scenario
Pick/Pack Time | Loading Time | Replenishment Lead Time [RLT] | Check W/O RLT [Tcode-OVZ9] | Transportation Lead Time | Transit Time | Complete Delivery by Law | Sale Order Quantity | Material Available Stock | Confirmed Quantity | Sale Order Date | Customer Requested Delivery Date | Backward Schedule Status | Forward Schedule Status | |
Scenario - 1 | YES | YES | Not Relevant | Not Relevant | NO | NO | NO | 10 | 100 | 10 | 17.09.2021 | 18.09.2021 | Fail | Success |
Scenario - 2 | YES | YES | Not Relevant | Not Relevant | NO | NO | NO | 50 | 100 | 50 | 18.09.2021 | 25.09.2021 | Success | #NA |
Scenario - 3 | YES | YES | YES | Uncheck | NO | NO | NO | 50 | 0 | 50 | 18.09.2021 | 25.09.2021 | Fail | Success |
Scenario - 4 | YES | YES | YES | Uncheck | NO | NO | NO | 50 | 0 | 50 | 18.09.2021 | 03.10.2021 | Success | #NA |
Scenario - 5 | YES | YES | YES | Uncheck | NO | NO | NO | 150 | 100 | 100+50 | 19.09.2021 | 28.09.2021 | Success | Success |
Scenario - 6 | YES | YES | YES | Uncheck | NO | NO | NO | 150 | 100 | 150 | 19.09.2021 | 10.10.2021 | Success | #NA |
Scenario – 7 | YES | YES | YES | Uncheck | NO | NO | NO | 150 | 100 | 100+50 | 19.09.2021 | 22.09.2021 | Fail | Success |
Scenario – 8 | YES | YES | YES | Uncheck | NO | NO | YES | 150 | 100 | 150 | 19.09.2021 | 22.09.2021 | Fail | Success |
Scenario – 9 | YES | YES | YES | Uncheck | NO | NO | YES | 150 | 100 | 150 | 19.09.2021 | 05.10.2021 | Success | #NA |
Scenario – 10 | YES | YES | NO [No Scope for producing the goods] | Check | NO | NO | NO | 150 | 100 | 100 | 19.09.2021 | 28.10.2021 | Success | #NA |
Scenario – 11 | YES | YES | NO [No Scope for producing the goods] | Check | NO | NO | NO | 150 | 100 | 100 | 22.09.2021 | 25.10.2021 | Fail | Success |
Scenario – 12 | YES | YES | NO [No Scope for producing the goods] | Check | NO | NO | NO | 150 | 0 | 100 | 21.12.2021 | 21.01.2022 | Fail | Not Relevant |
Scenario – 13 | YES | YES | YES | Uncheck | YES | YES | NO | 60 | 100 | 60 | 24.09.2021 | 07.10.2021 | Fail | Success |
Scenario – 14 | YES | YES | YES | Uncheck | YES | YES | NO | 60 | 100 | 60 | 24.09.2021 | 13.10.2021 | Success | #NA |
Scenario – 15 | YES | YES | YES | Uncheck | YES | YES | NO | 60 | 0 | 60 | 26.12.2021 | 11.01.2022 | Fail | Success |
Scenario – 16 | YES | YES | YES | Uncheck | YES | YES | NO | 60 | 0 | 60 | 26.12.2021 | 24.01.2022 | Success | #NA |
NOTE: 1. When Backward Scheduling fails, system determines two Schedule lines.
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | ||||||||
3. Sale Order Creation Date | |||||||||
4. Backward Delivery Scheduling Fails As To be Sale Order date [13.09.2021] is beyond today’s date, Backward Scheduling Fails [Sales Order Quantity is not Confirmed]
| |||||||||
5. Backward Delivery Scheduling Process
| |||||||||
6. Forward Delivery Scheduling Success Forward Scheduling is determined based on Current Sale Order date + Pick pack days + Loading days [Sales Order Quantity Confirmed] | |||||||||
7. Forward Delivery Scheduling Process In this scenario, Delivery Creation date – 20.09.2021 P.G.I date – 22.09.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | ||||||||
3. Sale Order Creation Date | |||||||||
4. Backward Delivery Scheduling Fails As To be Sale Order date creation date [20.09.2021] is after today’s date [18.09.2021], Backward Scheduling success [Sales Order Quantity Confirmed] | |||||||||
5. Backward Delivery Scheduling Process In this scenario, Delivery Creation date – 20.09.2021 P.G.I date – 25.09.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack and Loading Time | ||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | ||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked
| |||||||||||
6. Backward Delivery Scheduling Fails As To be Sale Order date creation date [10.09.2021] is beyond today’s date [18.09.2021], Backward Scheduling Fails [Sales Order Quantity Not Confirmed]
| |||||||||||
7. Backward Delivery Scheduling Process
| |||||||||||
8. Forward Delivery Scheduling Success Forward Scheduling is determined based on Current Sale Order date + Pick pack days + Loading days + R.L.T days [Sales Order Quantity Confirmed]
| |||||||||||
9. Forward Delivery Scheduling Process In this scenario, System considers R.L.T – 10 days, as the Material stock is not available. Delivery Creation date – 28.09.2021 P.G.I date – 03.10.2021
|
1. Customer Requested Delivery Date
| 2. Pick Pack – Loading Time
| |||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked
| ||||||||||||
6. Backward Delivery Scheduling Success | ||||||||||||
7. Backward Delivery Scheduling Process In this scenario, System considers R.L.T - 10 days, as the Material stock is not available still the Customer Requested Delivery date is met. Delivery Creation date – 28.09.2021 P.G.I date – 03.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack and Loading Time | ||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | ||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked
| |||||||||||
6. Backward Scheduling Partially Success In this scenario the Customer Requested Delivery date is met for 100 Quantity and for the rest 50 qty Backward Scheduling is fail.
| |||||||||||
7. Backward Delivery Scheduling Process In this Scenario, Delivery Creation date – 23.09.2021 P.G.I date – 28.09.2021 for 100 quantity
| |||||||||||
8. Forward Delivery Scheduling Success For 50 qty Forward Scheduling is Pass. | |||||||||||
9. Forward Delivery Scheduling Process In this scenario system considers R.L.T - 10 days, as the Material stock is not available for 50 qty. And Delivery Creation date – 29.09.2021 P.G.I date – 04.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time
| |||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked
| ||||||||||||
6. Backward Delivery Scheduling Success In this scenario the Customer Requested Delivery date is met for total 150 Quantity, so Backward Scheduling Success. | ||||||||||||
7. Backward Delivery Scheduling Process And Delivery Creation date – 05.10.2021 P.G.I date – 10.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack and Loading Time | ||||||||||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | ||||||||||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked
| |||||||||||||||||||
6. Backward Delivery Scheduling Fails In this scenario the Customer Requested Delivery date not met for total 150 Quantity, so Backward Scheduling Fails. | |||||||||||||||||||
7. Backward Delivery Scheduling Process
| |||||||||||||||||||
8. Forward Delivery Scheduling Success Forward Scheduling is Success, for 100 and 50 qty there will be different Confirmation dates as based on Material stock availability. | |||||||||||||||||||
9. Forward Delivery Scheduling Process For 100 Qty Delivery Creation date for 100 qty – 19.09.2021 P.G.I date – 24.09.2021
For 50 Qty Delivery Creation date for 50 qty – 29.09.2021 P.G.I date – 04.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked | 6. Complete Delivery Required by Law in Customer Master/Sales Area data
| |||||||||||
7. Backward Delivery Scheduling Fails In this scenario the Customer Requested Delivery date not met for total 150 Quantity, so Backward Scheduling Fails. | ||||||||||||
8. Backward Delivery Scheduling Process
| ||||||||||||
9. Forward Delivery Scheduling Success Forward Scheduling is Success for 150 qty at a time, not partial delivery allowed as per Customer requirement, so the total quantity is confirmed at a time. | ||||||||||||
10. Forward Delivery Scheduling Process For 100 Qty Delivery Creation date for150 qty – 29.09.2021 P.G.I date – 04.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View
| |||||||||||
5. Availability Check Control For not to consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked | 6. Complete Delivery Required by Law in Customer Master/Sales Area data | |||||||||||
7. Backward Delivery Scheduling Success In this scenario the Customer Requested Delivery date met for total 150 Quantity, so Backward Scheduling Success. | ||||||||||||
8. Backward Delivery Scheduling Process Delivery Creation date for150 qty – 29.09.2021 P.G.I date – 05.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View
| |||||||||
5. Availability Check Control To consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be checked
| ||||||||||
6. Backward Scheduling Partially Fail and Partially Success: In this scenario the Customer Requested Delivery date met only for 100 Quantity, and ‘Check Without R.L.T’ is checked so system did not consider the Production plan, so it did not confirm the rest 50 quantity and Backward Scheduling Success for 100 qty and fails for 50 qty. | ||||||||||
7. Backward Delivery Scheduling Process Delivery Creation date for 100 qty – 23.09.2021 P.G.I date – 28.09.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||
5. Availability Check Control To consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be checked | ||||||||||
6. Backward Delivery Scheduling Fails In this scenario the Customer Requested Delivery date not met so Backward Scheduling Fails. | ||||||||||
7. Backward Delivery Scheduling Process
| ||||||||||
8. Forward Delivery Scheduling Success Forward Scheduling is Success for 100 qty and as RLT is checked, system would not consider the time for Production Planning and that’s why 50 qty is neither confirmed nor shown in the system.
| ||||||||||
9. Forward Delivery Scheduling Process For 100 Qty Delivery Creation date for100 qty – 22.09.2021 P.G.I date – 27.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |
5. Availability Check Control To consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be checked | ||
6. Backward Delivery Scheduling Fails In this scenario the Customer Requested Delivery date not met for 150 Quantity so Backward Scheduling Fails, and R.L.T is checked so system did not consider the Production plan, so it did not confirm the rest 150 quantity. | ||
7. Backward Delivery Scheduling Process There is no process of Backward or Forward Scheduling, as there is no scope for waiting period to be considered for this specific order to be processed and delivered, it is the Customer Requirement. |
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | ||||||||||
3. Sale Order Creation Date | |||||||||||
4. Backward Delivery Scheduling Fails In this scenario the Customer Requested Delivery date not met for 60 Quantity so Backward Scheduling Fails because system considers, Transportation Lead Time [7 days] + Loading Time [2 days] + Transit Time [5 days] | |||||||||||
5. Backward Delivery Scheduling Process
| |||||||||||
6. Forward Delivery Scheduling Success Forward Scheduling is Success for 60 qty. | |||||||||||
7. Forward Delivery Scheduling Process Delivery Creation date for 60 qty – 24.09.2021 P.G.I date – 03.10.2021 Customer Goods Receiving date – 09.10.2021
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | ||||||||||
3. Sale Order Creation Date | |||||||||||
4. Backward Delivery Scheduling Success In this scenario the Customer Requested Delivery date met for 60 Quantity so Backward Scheduling Success. | |||||||||||
5. Backward Delivery Scheduling Process Delivery Creation date for 60 qty – 30.09.2021 P.G.I date – 08.10.2021 Customer Goods Receiving date – 13.10.2021
|
1. Customer Requested Delivery Date
| 2. Pick Pack – Loading Time | |||||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||||||
5. Availability Check Control To consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked | ||||||||||||||
6. Backward Delivery Scheduling Fails | ||||||||||||||
7. Backward Delivery Scheduling Process Proposed SO creation date going beyond today’s date so Backward Scheduling Fails
| ||||||||||||||
8. Forward Delivery Scheduling Success Forward Scheduling is Success for 60 qty. | ||||||||||||||
9. Forward Delivery Scheduling Process And Delivery Creation date for 60 qty – 24.09.2021 P.G.I date – 03.10.2021 Customer Goods Receiving date – 09.10.2021 Note: Instead of 08.10.2021 system proposes Customer Goods Receiving date as 09.10.2021, is because on 02.10.2021 the respective Calendar states the Holiday.
|
1. Customer Requested Delivery Date | 2. Pick Pack – Loading Time | |||||||||||||
3. Sale Order Creation Date | 4. Replenishment Lead Time [R.L.T] It will be maintained in Material Master MRP3 View | |||||||||||||
5. Availability Check Control To consider the RLT Days in Delivery Schedule from Material Master, “Check without RLT” in Tcode-OVZ9 should be Un checked | ||||||||||||||
6. Backward Delivery Scheduling Success In this scenario the Customer Requested Delivery date met for 60 Quantity so Backward Scheduling Success. | ||||||||||||||
7. Backward Delivery Scheduling Process Delivery Creation Date OR Transportation Planning Date – 10.01.2021 P.G.I date – 19.01.2022 Customer Goods Receiving Date – 24.01.2022
|